Mismanagement of Procurement

September 17, 2008 |  Investigative Summaries

"Amtrak Management was aware of a fatally flawed contract provision which required the vender to complete and Environmental Impact Study ("EIS") and Environmental Impact Report ("EIR") within a requisite 270 days (nine months). This restriction was, by admission of [REDACTED], an impossible task."

Tracking Number

I-04-187