March 15, 2011 |  Audit Reports

Operation RedBlock: Actions Needed to Improve Program Effectiveness

Our objectives were to determine the progress made by the company in implementing the recommendations made in our March 2008 evaluation report and to… Read more
Tracking Number

E-11-01

January 14, 2011 |  Audit Reports

Strategic Asset Management Program Controls Design Is Generally Sound, But Improvements Can Be Made

Our audit objective was to review SAM program’s internal controls design to determine whether it adequately identified and mitigated internal control… Read more
Tracking Number

105-2010

January 12, 2011 |  Audit Reports

Price Proposal Audit: Amtrak Should Negotiate a Price Adjustment to a Major Acquisition Contract

Our audit objectives were to determine whether (1) the data were current, accurate, and complete; (2) the contractor’s internal controls were… Read more
Tracking Number

219-2010

December 22, 2010 |  Audit Reports

Incurred Cost Audit: Amtrak's Track Replacement and Related Improvements Contracts

We're sorry, but currently there is no summary for this report. Please click on the download button to view the entire report in PDF format.
Tracking Number

504-2009

December 13, 2010 |  Audit Reports

Incurred Cost Audit: Amtrak's Design/Build Improvements Contract (Summary)

Our audit objective was to determine the accuracy and acceptability of costs invoiced by the Contractor.
Tracking Number

503-2009

December 02, 2010 |  Audit Reports

Questionable Contract Language Related to Interest Payable Under Kiewit Contract Sounder Preventive Maintenance Track Replacement and Related Improvements, Seattle, WA and Kiewit Contract South End Track and Related Improvements, Seattle, WA

Our objective for the two audits was to determine the accuracy and acceptability of costs billed by Kiewit Pacific Co. The audit results related to… Read more
Tracking Number

508-2009

November 02, 2010 |  Audit Reports

Memo to Withdraw the Attleboro Pawtucket Agreement Review

We are withdrawing the subject report. Shortly after publishing the report on September 30, 2009, we became aware of questions about the accuracy of… Read more
Tracking Number

205-2009

September 24, 2010 |  Audit Reports

BNSF On-time Performance Incentives

Our audit objective was to determine whether BNSF complied with the Agreement, Appendix V, which provides the basis for performance payments and to… Read more
Tracking Number

407-2003

August 17, 2010 |  Audit Reports

Amtrak's Strategic Planning

Originally, we planned to evaluate Amtrak’s Strategic Planning process and the 2009 planning documents by comparing and contrasting the process and… Read more
Tracking Number

E-10-01

May 28, 2010 |  Audit Reports

Amtrak OIG FY2010 Recovery Act Work Plan

Our overall goals are to: 1) ensure that programs proposed by Amtrak meet legislative candidacy requirements; 2) Program are well managed, 3) Risks… Read more
Tracking Number

RA-018